2025_Risk-Based_Change_Management_Process_Control_100120

Edit Project

Start Date: 2025-10-04

End Date: 2025-12-09

Duration: 67 days

Total Hours: 109.4

Audit Plan: Annual Audit Plan 2025 (2025)

Assigned Employees: 8

Description

Project focusing on Change Management Process as part of the Risk-Based Control cycle for 2025.


Assigned Employees
Employee Team Start Date End Date Total Hours Utilization Actions
Henry Lehtinen Financial Audit / Internal Controls 2025-11-17 2025-12-08 12.9
0.8%
12.9 of 1566.0 hours (0.87 ratio)
Aksel Adams Operational Audit / Process Improvement 2025-11-11 2025-11-27 11.8
0.7%
11.8 of 1710.0 hours (0.95 ratio)
Elias Garcia Financial Audit / SOX Compliance 2025-10-22 2025-11-12 9.0
0.7%
9.0 of 1332.0 hours (0.74 ratio)
Jacob Nelson Operational Audit / Process Improvement 2025-11-13 2025-11-30 11.8
0.9%
11.8 of 1386.0 hours (0.77 ratio)
James Olsson IT Audit / Cybersecurity 2025-10-21 2025-11-08 24.5
1.5%
24.5 of 1674.0 hours (0.93 ratio)
Oscar Lewis IT Audit / Infrastructure Security 2025-11-14 2025-11-28 12.3
0.8%
12.3 of 1566.0 hours (0.87 ratio)
Emil Anderson Financial Audit / Revenue Assurance 2025-11-20 2025-11-28 11.3
0.7%
11.3 of 1530.0 hours (0.85 ratio)
Madison Larsen Financial Audit / SOX Compliance 2025-11-14 2025-12-05 11.1
0.8%
11.1 of 1422.0 hours (0.79 ratio)

Assign Employee