2025_Emergency_HR_Processes_Review_100003

Edit Project

Start Date: 2025-05-11

End Date: 2025-07-04

Duration: 55 days

Total Hours: 643.0

Audit Plan: Annual Audit Plan 2025 (2025)

Assigned Employees: 3

Description

Project focusing on HR Processes as part of the Emergency Review cycle for 2025.


Assigned Employees
Employee Team Start Date End Date Total Hours Utilization Actions
Aksel Garcia Financial Audit / Internal Controls 2025-05-15 2025-06-17 500.0
37.0%
500.0 of 1350.0 hours (0.75 ratio)
Adam Nowak Financial Audit / Internal Controls 2025-05-14 2025-05-18 102.0
7.5%
102.0 of 1368.0 hours (0.76 ratio)
Emma Williams IT Audit / Application Controls 2025-06-07 2025-06-19 66.0
4.0%
66.0 of 1656.0 hours (0.92 ratio)

Assign Employee

Total hours for the entire assignment period