2025_Proactive_API_Security_Remediation_100046

Edit Project

Start Date: 2025-09-01

End Date: 2025-11-04

Duration: 65 days

Total Hours: 497.5

Audit Plan: Annual Audit Plan 2025 (2025)

Assigned Employees: 8

Description

Project focusing on API Security as part of the Proactive Remediation cycle for 2025.


Assigned Employees
Employee Team Start Date End Date Total Hours Utilization Actions
Jakob Sanchez IT Audit / Application Controls 2025-10-09 2025-10-23 41.5
3.1%
41.5 of 1350.0 hours (0.75 ratio)
Sofia Johnson Compliance & Risk / Regulatory Compliance 2025-09-01 2025-09-27 71.3
4.2%
71.3 of 1710.0 hours (0.95 ratio)
Ella Mäkinen Operational Audit / Supply Chain Audit 2025-09-14 2025-09-30 70.2
4.7%
70.2 of 1494.0 hours (0.83 ratio)
Samuel Clark IT Audit / Application Controls 2025-10-17 2025-11-03 64.4
4.6%
64.4 of 1404.0 hours (0.78 ratio)
Emma Williams IT Audit / Application Controls 2025-10-07 2025-11-01 90.4
5.5%
90.4 of 1656.0 hours (0.92 ratio)
Leo Young Financial Audit / Internal Controls 2025-10-17 2025-10-30 56.0
4.3%
56.0 of 1314.0 hours (0.73 ratio)
Szymon Johansson IT Audit / Infrastructure Security 2025-09-23 2025-10-17 50.4
3.8%
50.4 of 1332.0 hours (0.74 ratio)
Isabella Jørgensen Compliance & Risk / Vendor Risk 2025-10-01 2025-10-29 41.8
3.1%
41.8 of 1368.0 hours (0.76 ratio)

Assign Employee

Total hours for the entire assignment period