2025_Follow-up_Intellectual_Property_Protection_Optimization_100096
Edit ProjectStart Date: 2025-03-22
End Date: 2025-05-18
Duration: 58 days
Total Hours: 280.2
Audit Plan: Annual Audit Plan 2025 (2025)
Assigned Employees: 8
Description
Project focusing on Intellectual Property Protection as part of the Follow-up Optimization cycle for 2025.
Assigned Employees
Employee | Team | Start Date | End Date | Total Hours | Utilization | Actions |
---|---|---|---|---|---|---|
William Kozlowski | Operational Audit / Process Improvement | 2025-04-01 | 2025-04-23 | 36.7 |
|
|
Aurora Larsson | Compliance & Risk / Regulatory Compliance | 2025-05-01 | 2025-05-05 | 37.0 |
|
|
Maja Sørensen | IT Audit / Application Controls | 2025-04-15 | 2025-05-14 | 40.4 |
|
|
Oliver Nieminen | IT Audit / Application Controls | 2025-04-29 | 2025-05-08 | 49.5 |
|
|
Alma Andersen | Operational Audit / Supply Chain Audit | 2025-03-27 | 2025-04-07 | 58.5 |
|
|
Joseph Mazur | Financial Audit / SOX Compliance | 2025-03-27 | 2025-04-18 | 43.2 |
|
|
Henrik Harris | IT Audit / Application Controls | 2025-04-30 | 2025-05-16 | 34.7 |
|
|
Antoni Eriksen | Compliance & Risk / Regulatory Compliance | 2025-04-10 | 2025-04-18 | 26.7 |
|